Belconnen trunk sewer update to BCC:

Icon Water recognise that it is a challenging time for our community – it is understood that with so much going on that this work is unlikely to be of priority, so are providing only a high level summary of where things are up to. Whilst the project is currently still on track with construction likely to commence in late 2020, it is possible that this may be delayed due to impacts of COVID-19.

Thank you to everyone who provided feedback on the projects. Icon Water are committed to keeping the Belconnen community informed and have kept our website up to date based on feedback and questions we have received. We encourage those who want to know more to see the website (iconwater.com.au/bts) any questions can be emailed to [email protected] or you can talk to us on 6248 3111 (option 9). If you would like to receive updates on the project, please sign up on the website.

Project updates:

·       The DAs for Projects 2 (Latham Odour Control Unit – OCU) and 3 (Florey OCU) were lodged with EPSDD in December 2019. Approval was received for Project 2 in March and it is expected that approval will soon follow for Project 3.  Approval for Project 4 (Evatt OCU) was received in February.  

·       The revised Environmental Impact Statement (EIS) is being prepared for Project 1 (2.4 km pipeline and odour control unit (OCU) at North Latham) and it is expected that the EIS and concurrent Development Application (DA) will be resubmitted later this month. Community feedback regarding the DA can be made directly to EPSDD during a 15 day notification period. Icon Water will provide update to those who have registered interest in the projects (including the Belconnen Community Council) when this occurs.

·       Sewer bridge over Ginninderra Creek. During the notification period for the draft EIS on the pipeline, there was feedback received suggesting that the a pedestrian and cycle bridge could be installed over the planned sewer bridge in Melba above Ginninderra Creek. Cost of a footbridge needs to be balanced against benefit realised to the Canberra community. Options are currently being assessed and will be incorporated in the revised EIS.

·       Delany Court playground in Melba.  Icon Water had originally planned to consult with the community regarding whether this playground should be relocated, however following feedback, a decision has been made to have the playground remain in its current location. Consequently, during construction of the trunk sewer pipe the existing playground will be dismantled. Following installation of the new trunk sewer a new playground will be constructed in the existing site (at the end of Delany Court). This will involve some downtime for the playground of up to six months.

If you have questions, please have a look at the Icon Water website (iconwater.com.au/bts), send an email [email protected] or give them a call on 6248 3111 (option 9). There is also information on the website about Icon Water’s response to COVID-19 including advice on support that is available to customers.